Furniture Quote Audit Before the PO: Versions, Formulas and Dates

An anonymized audit of two 20-item furniture planning sheets and a blank schedule, with a practical pre-PO checklist.

Updated by the Source Foshan sourcing team in Foshan.

Dark upholstered sofa on display, illustrating the need to quote the exact fabric and configuration
A displayed sofa from Source Foshan’s licensed company archive. Illustrative only; no price or construction claim is inferred from the photograph.
Direct answer

Before a furniture purchase order, reconcile every quote version, item specification and total formula; then check what event starts the schedule. A filled price and a lead-time label do not establish an approved order.

Original document audit · Two 20-item working copies + one blank schedule · No signed transaction outcome

Evidence scope. We reviewed two variants of one internal planning worksheet and a separate uncommenced schedule template. The figures below show document structure only. Client and supplier identities, product details and prices are withheld; neither worksheet is verified as a final supplier offer.

1. What the planning worksheet actually contained

We reviewed two near-identical copies of an internal furniture planning worksheet, each with 20 item rows. One labels its unit prices as estimated ex-factory prices; the other uses a less clear currency heading. All 20 unit-price cells differ between copies, while their item labels, quantities, product-dimension entries and line-total formulas match. Neither copy identifies itself as the signed final offer. We cannot infer which price set was approved, whether either was sent to a supplier, or whether a later document corrected the gaps.

In the copy used for the chart below, quantity, unit price, a line-total formula and a “60” lead-time entry appeared on all 20 rows. Yet the material/specification and packed-weight columns were empty throughout. Only 11 rows contained anything in the product-dimension field, generally a single measurement rather than the stated length × width × height. The entries mixed inch marks and metres under a millimetre header. The other copy shared those counts except that its two carton-dimension conversion formulas were also absent.

The version-control questionWhen two working copies have the same item list but different prices, a buyer needs a dated, attributable revision and an approval record before using either total. A filename suffix or file-system timestamp is not proof that one copy supersedes the other.

This is a worksheet-completion audit, not a supplier-performance sample. A blank field may have been resolved in a drawing or correspondence elsewhere. Until those records are linked by model and revision, the worksheet alone cannot support approval.

Visual 01 · Which buyer-critical fields were populated?20 item rows
Estimated unit price20/20
Lead-time entry20/20
Product dimension field11/20
Carton dimension field2/20
Material / specification0/20
Packed weight0/20
Counts are non-empty cells in the version with two carton-dimension conversion formulas. The other version has 0/20 in that field. Populated entries are not necessarily complete or validated; a single dimension and a price do not define a SKU.
Buyer decisionRequest one controlled specification record per line: model/revision, material and finish, full product dimensions with units, packed dimensions and weight, quantity, included hardware, and a drawing or sample approval reference. Re-price only after those fields are fixed.
Table and cabinet in a furnished interior, illustrating why a photograph needs a stable model reference
A furniture setting from Source Foshan’s company archive. It illustrates product identity; none of the pictured items is asserted to appear in the audited worksheets.

2. Recalculate the total; do not trust the “Total” label

Both worksheet variants use the same final total formula, which sums line totals from rows 3 through 18. The item list continues through row 22. That leaves four line items outside the total formula. We do not publish the private prices, but the structural error matters even if every unit price were agreed: the displayed total would not represent all 20 items.

Visual 02 · Formula coverage versus item listRows 3–22
03
04
05
06
07
08
09
10
11
12
13
14
15
16
17
18
19
20
21
22
Included in SUM(M3:M18)Not included in the final formula
Source formula was examined directly in the workbook. We did not infer an amount from this error or treat the working file as a final invoice.

For an order review, compare the number of item rows with the formula range, recalculate quantity × approved unit price by line, and reconcile the total against the supplier’s final quotation. If the quantity changes later, recheck formulas that contain hard-coded multipliers.

3. Make dimensions computable before discussing freight

The product-dimension header specified “L × W × H mm,” but populated cells commonly held a single inch measurement. Two entries in the packaging-dimension column were inch-to-centimetre conversion formulas, even though that column also stated millimetres and asked for three dimensions. No package weight was entered. This is a unit and completeness problem, not evidence that a carton was incorrectly manufactured.

Visual 03 · One number does not answer three questionsUnit check
Worksheet shape
“108″”

One measurement in a field labelled L × W × H, with a millimetre header.

Orderable shape
L × W × H

Each measurement stated in one unit, tied to the exact model/revision; packed size and weight stated separately.

The value shown is one format found in the planning worksheet. It is an example of an unresolved field, not a published product specification.

Why it matters: the same unit ambiguity can flow into carton cube, loading, storage, door clearance and claims handling. The buyer should request a supplier-confirmed measurement sheet, then measure the approved sample and first packed unit against that version.

4. Audit the clock before repeating a delivery promise

A separate blank furniture schedule states 10 days for order confirmation, 60 for production and 30 for sea transit, then labels the total as 90 days. Those three sequential durations add to 100 days; the table itself ends at day 100. Every stage is marked “Not Commenced,” so this is a planning inconsistency, not evidence of a missed shipment.

Visual 04 · The schedule’s stated componentsPlanning template
10 + 60 + 30 = 100 days. The header said 90; the timeline ended at day 100.
Sequential addition is only a reading of this template. Real activities can overlap or vary. A customer-specific schedule needs dated milestones and clearly defined start/end events.

Before an order is placed, ask the supplier to define what “day 1” means: deposit receipt, signed drawings, material approval, or something else. Separate factory-ready date from vessel departure and arrival; define who owns delays caused by drawing changes, failed samples or customs. Treat the schedule as an agreed control record once both sides accept dates and owners.

Two upholstered chair samples in a workshop while a worker handles material in the background
Chair samples in a workshop from Source Foshan’s company archive. The image illustrates why sample and drawing references must match the purchase order; it is not an outcome record for the audited files.

5. A three-part release gate for the purchase order

These files would be useful working drafts. They are not yet a decision packet. The release gate below focuses on the three things the buyer could not verify from the files alone.

Visual 05 · What has to be fixed before approval?Decision gate
01 · Defined product

Every item has a controlled drawing or spec, material/finish, complete units, sample sign-off and pack data.

02 · Reconciled money

All item rows appear in the total; quantities and formulas match the final supplier quote and agreed currency/terms.

03 · Owned dates

Milestones add up, start events are defined, approvals have owners, and transit assumptions are identified.

If any gate remains open, record the exception and its owner. The purpose is to prevent an estimate or template from silently becoming a contractual promise.
Ask forMinimum usable answerWhat to do if missing
Revision-controlled product sheetModel, material, finish, L × W × H and units, drawing/sample referenceHold that line from final price approval
Packing sheetCarton count, outer L × W × H, gross weight, hardware and protectionDo not finalize freight/cube assumptions
Reconciled quoteEvery item × quantity × approved unit price, complete total and termsRecalculate and request a corrected version
Dated milestone scheduleStart trigger, sample/drawing approval, production finish, dispatch and transit basisLabel timing as provisional until agreed
Download the pre-PO audit checklist ↓

Method and limits

This review used two private variants of the same 20-item planning worksheet and one blank furniture-schedule PDF. We compared cell contents across variants, counted non-empty cells, checked formula references and compared the schedule header with its component durations and day range. A separate file named as a purchase order exists in the source folder, but its structure and item list do not establish a traceable revision chain to these two worksheets. We did not verify associated supplier correspondence, approved drawings, completed orders or final shipping records. Therefore this page reports document-readiness findings, not a defect rate, supplier failure, typical market lead time or actual delivery outcome.

That limit is also the point: a company can publish a useful original finding without dressing a planning file up as a completed case study. Once a finished order can be traced from quote to approved sample, packed item and receipt, the analysis can be updated with outcomes.

Put the guide to work

Send your list. We will tell you honestly how it would run.