Project Notes
Foshan to Orlando: 17 Pieces Delivered in May, Installed on 30 July When the House Was Ready — Packaging Cleared the Same Day
In short
- 01
Seventeen pieces for a new house in Orlando, Florida (32836): armchairs, a curved sofa set, marble nesting tables, library seating and a round marble table. The order did not fill a container, so we advised a consolidated (shared-container) load and re-crated the fragile pieces in timber.
- 02
The furniture arrived in May, but the house was still being finished. Rather than store it or push the client, the crew delivered the crates into the house on 19 May and left them sealed.
- 03
On 30 July, when the fit-out was done, the crew came back: unwrapped, assembled and positioned every piece between 16:40 and 16:55, and had the packaging on the truck by 17:02.
- 04
No chasing, no clutter, no second charge for waiting. The install happens when the client is ready.
Renovations run late. Ships do not wait. This Orlando client’s furniture was ready in Foshan months before the house was ready for it — a normal situation on a new build, and one where a shipment left to a freight forwarder usually ends up in paid storage, or standing in cardboard in the middle of a construction site. Here is how we handled the gap. Source Foshan consolidated the 17 pieces in Foshan, held them while the house was finished, and installed them when it was ready.
Photographs taken on site by the delivery crew; the clock and location stamps are from the site camera. Client details are withheld. Published by Source Foshan as a project note.
Some factories ship in a thin plywood case that is fine for a domestic truck and not fine for a shared container crossing the Pacific. Before this order left Foshan the fragile pieces were rebuilt into braced timber crates, and the whole order — all 17 pieces — was staged at our warehouse and checked as one shipment.



- Consolidation and re-crating
Pieces collected from their factories, fragile items re-crated, 17 crates staged as one shipment.
- Sea leg to Florida
Consolidated load — the client paid for the space used.
- Delivered into the house
Fit-out not finished. Crates carried inside, kept sealed, positioned out of the trades’ way.
- The house is finished
No storage fees, no reminders. The client told us when the floors and paint were done.
- Installation
Crates opened, pieces unwrapped, assembled and positioned room by room; packaging swept up.
- Packaging removed
Crates, cardboard and wrap loaded on the truck and taken away.











Seventeen pieces’ worth of crates, cardboard and film on the truck seven minutes after the last piece was positioned. The client kept the furniture, not the packaging.

Send us the quotation you were given. We will tell you what is missing from it.
A free second look from a local team that reads Foshan quotations every week: unit specs, add-on risks, packing and freight lines, payment terms. No commitment.
- Re-crate what the factory under-packs
Thin plywood becomes braced timber before it leaves Foshan. On a shared container this is the difference between a chipped marble edge and none.
- Install when the house is ready, not when the ship is
Crates delivered in and sealed in May; installed at the end of July. No storage bill, no pressure on the client’s renovation.
- A second visit is part of the plan
The crew that delivered came back to unwrap, assemble and position — the same team, so nothing was lost between visits.
- Clear-up is the last line item
Sweep the rooms, load the waste, leave. The install is not finished until the packaging is gone.
Questions buyers ask when the house is not ready
What happens if my furniture arrives before my house is finished?
Two options: hold it at the destination warehouse (which costs storage by the week) or, as here, deliver the sealed crates into a finished part of the house and install later. We scope the second visit up front so there is no surprise charge when the house is ready.
Can you split delivery and installation into two visits?
Yes. In this case the crates were delivered on 19 May and installed on 30 July 2026. The crates stay sealed between visits and the same crew comes back to unwrap, assemble and position.
Why re-crate furniture that the factory has already packed?
Factory packaging is designed for a domestic truck to a showroom. Shared (LCL) containers add forklift handling at both ends and weeks of movement at sea. Timber bracing around the wrapped piece is how marble, glass and veneered edges arrive intact — see export packing in our QC guide.
Planning a Foshan order that has to arrive assembled, not just arrive? Tell us the destination, the rooms and roughly how many pieces, and we will scope the buying trip, the packing and the door-to-door leg together — start your project, or read how consolidation and shipping and pre-shipment inspection work.